Gulf County Conditional Waiver and Release of Lien upon Progress Payment Form
Fill in the blank form formatted to comply with all recording and content requirements.

Gulf County Conditional Waiver and Release of Lien upon Progress Payment Guide
Line by line guide explaining every blank on the form.

Gulf County Completed Example of the Conditional Waiver and Release of Lien upon Progress Payment Form
Example of a properly completed form for reference.
All 3 documents above included • One-time purchase • No recurring fees
Immediate Download • Secure Checkout
Additional Florida and Gulf County documents included at no extra charge:
Where to Record Your Documents
Gulf County Clerk of Court - Courthouse
Port St. Joe, Florida 32456
Hours: 9:00am to 5:00pm M-F
Phone: (850) 229-6112 Ext. 1105 and 1117
Clerk's Annex Office
Wewahitchka, Florida 32465
Hours: 8:00am to 11:30 & 12:30 to 4:00pm M-F CS time
Phone: 850-639-2175
Recording Tips for Gulf County:
- Bring your driver's license or state-issued photo ID
- Ensure all signatures are in blue or black ink
- Recorded documents become public record - avoid including SSNs
- Recording fees may differ from what's posted online - verify current rates
- Request a receipt showing your recording numbers
Cities and Jurisdictions in Gulf County
Properties in any of these areas use Gulf County forms:
- Port Saint Joe
- Wewahitchka
Hours, fees, requirements, and more for Gulf County
How do I get my forms?
Forms are available for immediate download after payment. The Gulf County forms will be in your account ready to download to your computer. An account is created for you during checkout if you don't have one. Forms are NOT emailed.
Are these forms guaranteed to be recordable in Gulf County?
Yes. Our form blanks are guaranteed to meet or exceed the applicable formatting requirements used for recording in Gulf County, including margin requirements, font requirements, and other layout standards. This guarantee applies to formatting, not to the legal sufficiency of information entered by the user or the suitability of a form for a particular transaction.
Can I reuse these forms?
Yes. You can reuse the forms for your personal use. For example, if you have multiple properties in Gulf County you only need to order once.
What do I need to use these forms?
The forms are PDFs that you fill out on your computer. The free Adobe Acrobat Reader is recommended, and most PDF apps also work. You do NOT enter your property information online - you download the blank forms and complete them privately on your own computer.
Are there any recurring fees?
No. This is a one-time purchase. Nothing to cancel, no memberships, no recurring fees.
How much does it cost to record in Gulf County?
Recording fees in Gulf County vary. Contact the recorder's office at (850) 229-6112 Ext. 1105 and 1117 for current fees.
Questions answered? Let's get started!
The Florida Conditional Waiver and Release of Lien upon Progress Payment is the lienor-protective counterpart to the unconditional progress waiver in section 713.20 of the Florida Statutes. With this version, the release is contingent: the lien rights described in the form are released only when the identified progress payment is actually received and clears. If the customer's check bounces, is stopped, or never arrives, the waiver does not take effect and the lienor's lien rights remain intact. Florida codified four statutory waiver scenarios precisely so that lienors and payors can match the right risk allocation to the situation, and the conditional progress waiver is the standard choice when a contractor, subcontractor, or supplier wants to deliver a release simultaneously with the act of being paid without taking on the credit risk of the payment instrument.
What the Florida Conditional Waiver and Release of Lien upon Progress Payment Does
This form is exchanged on a Florida construction project by a lienor — anyone with a right to claim a construction lien under chapter 713 — for a specific interim payment toward labor, services, or materials furnished through a stated date. Calling it "conditional" means the lien release is contingent on actual receipt and clearance of the payment; calling it "progress" means it covers a partial billing during an ongoing job, not the closeout. It is the form most commonly used to accompany a monthly pay application, because it lets the lienor deliver a signed waiver alongside the request for payment without losing the leverage of the underlying lien rights if the funds never land.
Florida Statutory Requirements Under Section 713.20
Florida is one of a handful of states that legislates the wording of construction lien waivers. Section 713.20 sets out specific statutory text for four scenarios — conditional or unconditional, paired with progress or final payment — and instructs that any waiver "substantially follow" the language of the matching statutory form. A waiver that materially deviates from the statutory wording, or that mixes language from a different scenario, may not be treated as a section 713.20 waiver at all. That distinction matters because the statute supplies the conditional language that ties the release to receipt of the payment; rewriting it can quietly convert a conditional waiver into something that operates as an unconditional release, or into a generic contractual document with uncertain effect.
The form must identify the lienor, the customer, the property owner, the amount of the conditional payment, the date through which the waiver applies, and a description of the property — typically the parcel identifier and legal description (§ 713.20).
Execution: No Witnesses, No Notary Required
Statutory waiver forms under section 713.20 do not require witnesses, notarization, or an acknowledgment to be effective. The lienor signs and dates the form, and it is delivered as part of the payment exchange. This is a deliberate departure from the formality required for Florida deeds, which need two witnesses and a notary; lien waivers move with the payment cycle on a job, and the legislature kept the execution requirements light. Some construction lenders and large general contractors require notarized waivers as a matter of internal policy. A notarized waiver is not invalid — the statute simply does not require notarization to make a section 713.20 waiver effective.
Florida-Specific Traps
Several features of the conditional progress waiver routinely surprise out-of-state contractors and owners:
- Advance waivers are void. Florida law prohibits waiving the right to claim a lien before the underlying labor, services, or materials are furnished. A waiver tied to work the lienor has not yet performed is unenforceable to that extent (§ 713.20).
- "Substantially follow" is a real test. A waiver missing a required field, or with the conditional language watered down, may not function as a section 713.20 conditional waiver. The customer who accepts a non-conforming waiver may have to pay twice if the underlying check is dishonored and the lienor's lien rights were never actually released.
- The condition is automatic. The customer does not have a clean release in hand until the payment actually clears. This is the trade-off baked into a conditional waiver — the lienor stays protected, but the payor cannot use the waiver alone as proof that lien exposure has been eliminated for the period covered. Final closeouts and lender funding reviews often demand unconditional waivers for that reason.
- Through date discipline. The form covers work through a stated date. A blank, postdated, or sloppily chosen through date can release more or less than the parties intended and creates evidentiary problems if the project later goes into dispute.
- Notice of Commencement alignment. Florida requires the owner to record a Notice of Commencement on most private projects before construction begins (§ 713.13). The property described in the waiver should match the property described in the Notice of Commencement so that waivers can be tied back to the underlying job.
- Joint check timing. If the progress payment is delivered by joint check, the conditional waiver only takes effect when the lienor is actually paid its share. A signed waiver does not bypass the joint payee's endorsement requirement.
How the Waiver Is Used
The conditional progress waiver is not recorded in the county's official records. It is delivered to the party making the payment — typically the general contractor, owner, or construction lender — and kept with the draw documentation. Because the release is contingent on payment receipt, owners and lenders often track conditional waivers against bank confirmations of cleared funds, and may swap them for unconditional waivers once the check has actually cleared. That two-step approach is common on jobs where the lender insists on documenting unconditional releases for audit purposes.
Download Package
The download package includes the Florida Conditional Waiver and Release of Lien upon Progress Payment, drafted to follow the statutory wording at section 713.20, a completed example showing how each field is filled in, and a guide explaining the form's conditional structure, the statutory framework, and how the four section 713.20 waiver scenarios fit together. The forms are prepared by Deeds.com's forms development team and are delivered as instant downloads.
Important: Your property must be located in Gulf County to use these forms. Documents should be recorded at the county recording office listed above.
This Conditional Waiver and Release of Lien upon Progress Payment meets all recording requirements specific to Gulf County.
Our Promise
The documents you receive here are guaranteed to meet or exceed the applicable Gulf County recording format requirements. If there is a rejection caused by our formatting, we will correct the issue or refund your payment. This guarantee applies to document formatting only and does not extend to information entered by the user, the selection of the form, or the legal effect of the completed document.
Save Time and Money
Get your Gulf County Conditional Waiver and Release of Lien upon Progress Payment form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.
4.8 out of 5 - ( 4,819 Reviews )
john m. 5 out of 5 stars
its a bit confusing for a novice computer user. I would prefer to print out the forms, fill them out on paper, then attach them to an email to discuss the accuracy of the forms with a friend, and then take the completed forms to the County office to be recorded
Thank you for your feedback. We really appreciate it. Have a great day!
Arthur L. 5 out of 5 stars
The directions were clear, I typed the deed out and it was successfully recorded and mailed back to me in less than a week.
Thank you for your feedback. We really appreciate it. Have a great day!
Michelle I. 5 out of 5 stars
I'm happy to have found your service. Very pleased.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Michael D. 1 out of 5 stars
I sent Deeds.com an email with a question, asking for a little guidance as to which form(s) I need, but I'm waiting for a reply. My wife and I own 3 homes (2 in Indiana & 1 in Florida). We are needing to deed each to ourselves and put them into our living trust. I asked Deeds.com to please help by suggesting which forms I need for this. I do not want to get the wrong ones. I have not received a reply yet. When I receive a helpful reply and am able to purchase the correct forms, I am fairly certain my rating will go from 1 to 5. I withhold judgement until later.
Thank you for your feedback Michael. We make available do it yourself deed documents. We do not prepare documents or provide legal advice. If you have done research and are still unsure of which documents you need we are not the website for you. We highly recommend seeking the advice of a legal professional familiar with your specific situation moving forward. Have a wonderful day.
Claudia H. 5 out of 5 stars
***** Have not used this option before. Found it easy to use and understand. Cost was reasonable and options on recording helpful. Would use again in a heartbeat.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Carol N. 1 out of 5 stars
Not helpful couldn't find anything
Thank you for your feedback Carol. Sorry to hear that you could not find what you were looking for. Have a wonderful day.
Linda M. 5 out of 5 stars
The form I purchased along with the instructions and completed sample were easy to use. I downloaded them on my iPad. I had to also download the free adobe reader app from the App Store. I had no problem getting the beneficiary deed recorded at the recorder’s office. I am pleased with my purchase.
Thanks so much for the kind words, Linda! Glad the sample and instructions made the process smooth, and that tip about the Adobe Reader app for iPad is genuinely helpful for other customers too. Congrats on getting the deed recorded!
Henry J. 5 out of 5 stars
Worked out Great!
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Caroline W. 5 out of 5 stars
They didn't have what I needed, but they were very quick in responding to let me know and where I needed to go to receive the desired information.
Thank you for your feedback Caroline.
Alicia S. 5 out of 5 stars
It's been a difficult time during my divorce. Glad I was able to get the house related documents easily here.
Thank you!
Antonia J. 5 out of 5 stars
Great Family Planner
Thank you!
Luz G. 5 out of 5 stars
very user friendly
Thank you for taking a moment to share your thoughts.
april m. 2 out of 5 stars
Could not give me any deed history prior to 1986, when our company bought the property, so this was a bust.
Thank you for your feedback April. Have a great day.
Oldemar T. 5 out of 5 stars
You guys simplified my life. You offer very convenient services. Thank you.
Thank you!
Michael S. 5 out of 5 stars
So convenient.
Knowing our customers are happy is our top priority. Thank you for the wonderful feedback!