Washington County Notice to Contractor Form
Last validated July 27, 2026 by our Forms Development TeamFormatted for recording in Washington County, for property anywhere in the county: rural and unincorporated areas as well as Caryville, Chipley, Ebro, Vernon, Wausau.
- 3 documents included
- Immediate PDF download
- Formatting guarantee

Washington County Notice to Contractor Form
Fill in the blank form formatted to comply with all recording and content requirements.

Washington County Notice to Contractor Guide
Line by line guide explaining every blank on the form.

Washington County Completed Example of the Notice to Contractor Document
Example of a properly completed form for reference.
All 3 documents above included • One-time purchase • No recurring fees
Immediate Download • Secure Checkout
Additional Florida and Washington County documents included at no extra charge:
Where to Record Your Documents
Washington County Clerk of Court
Chipley, Florida 32428
Hours: 8:00 to 4:00 M-F
Phone: (850) 638-6289
Recording Tips for Washington County:
- Bring your driver's license or state-issued photo ID
- Ensure all signatures are in blue or black ink
- Ask about accepted payment methods when you call ahead
- Ask for certified copies if you need them for other transactions
- Ask if they accept credit cards - many offices are cash/check only
Cities and Jurisdictions in Washington County
Properties in any of these areas use Washington County forms:
- Caryville
- Chipley
- Ebro
- Vernon
- Wausau
Hours, fees, requirements, and more for Washington County
How do I get my forms?
Forms are available for immediate download after payment. The Washington County forms will be in your account ready to download to your computer. An account is created for you during checkout if you don't have one. Forms are NOT emailed.
Are these forms guaranteed to be recordable in Washington County?
Yes. Our form blanks are guaranteed to meet or exceed the applicable formatting requirements used for recording in Washington County, including margin requirements, font requirements, and other layout standards. This guarantee applies to formatting, not to the legal sufficiency of information entered by the user or the suitability of a form for a particular transaction.
Can I reuse these forms?
Yes. You can reuse the forms for your personal use. For example, if you have multiple properties in Washington County you only need to order once.
What do I need to use these forms?
The forms are PDFs that you fill out on your computer. The free Adobe Acrobat Reader is recommended, and most PDF apps also work. You do NOT enter your property information online - you download the blank forms and complete them privately on your own computer.
Are there any recurring fees?
No. This is a one-time purchase. Nothing to cancel, no memberships, no recurring fees.
How much does it cost to record in Washington County?
Recording fees in Washington County vary. Contact the recorder's office at (850) 638-6289 for current fees.
Questions answered? Let's get started!
Florida's construction lien law splits payment-protection notices into two parallel tracks, and the Florida Notice to Contractor belongs to one of them. When a general contractor has furnished a statutory payment bond under FLA. STAT. 713.23 — recorded with the notice of commencement before work begins — a subcontractor or supplier not in direct contract with the general contractor cannot rely on the standard Notice to Owner. The bond replaces the property as the security for payment, and the document that perfects a claim against that bond is the Notice to Contractor. Sending the wrong notice, or sending the right notice late, eliminates the bond as a payment source.
What the Florida Notice to Contractor Does and When It Is Used
This notice tells the general contractor — and, in practice, the surety — that the lienor intends to look to the payment bond for protection on the work being supplied. It applies to private Florida construction projects where a 713.23 statutory payment bond has been recorded along with the notice of commencement. Material suppliers, sub-subcontractors, equipment lessors, and other lienors who are not contractually connected to the general contractor must serve this notice to preserve a claim. Laborers and parties in privity with the general contractor are excepted. Federal projects fall under the Miller Act and use a different mechanism entirely.
Statutory Requirements Under FLA. STAT. 713.23
The form identifies the parties and the project. At a minimum it names the owner who ordered the work, the general contractor coordinating the project, and the lienor furnishing labor or materials. It describes the real property where the improvement is being made and identifies the type of work or materials being supplied. The notice substantially follows the form set out in the statute (FLA. STAT. 713.23(1)(c)). Florida courts construe lien-law compliance strictly, and homemade variations risk being held insufficient.
The 45-Day Clock and Its Alternative
Timing is the trap that ends most bond claims. A lienor not in privity with the contractor — except a laborer — must serve the notice before beginning, or within 45 days after beginning, to furnish labor, materials, or supplies (FLA. STAT. 713.23(1)(c)). The clock runs from the first day of furnishing — not from the contract date and not from the purchase order.
An alternative window applies when the notice of commencement with the bond attached is not recorded before construction begins. In that situation, the lienor may serve the notice up to 45 days after being served with a copy of the bond (FLA. STAT. 713.23(1)(c)). A lienor who has not been provided a copy of the bond is entitled to demand one, and the statute imposes consequences on a party who refuses to furnish it.
Notice of Nonpayment — The Second Required Notice
The Notice to Contractor preserves the right to claim, but it is not the only notice the statute requires. Before bringing an action against the bond, the lienor must also serve a written notice of nonpayment on the contractor and the surety not later than 90 days after final furnishing of labor, services, or materials by the lienor (FLA. STAT. 713.23(1)(d)). The 90-day notice of nonpayment is a separate document with its own deadline; missing it eliminates the bond claim even when the initial Notice to Contractor was timely and correctly served.
How the Notice Must Be Served
Unlike many lien-related documents in Florida, the Notice to Contractor is served — not recorded with the county clerk. Service follows the methods authorized by FLA. STAT. 713.18: actual delivery to the person being served, or by common carrier delivery service or U.S. mail (registered, certified, or first-class with a certificate of mailing). Proof of service must be retained, because a bond claim that proceeds to litigation will turn on it.
Florida-Specific Traps
- Confusing the Notice to Contractor with the Notice to Owner. The Notice to Owner under FLA. STAT. 713.06 perfects a lien against real property on non-bonded jobs. The Notice to Contractor under 713.23 perfects a claim against a payment bond. They are not interchangeable, and using the wrong one on a bonded job is fatal to the claim.
- Statutory bond versus common law bond. Section 713.23 governs statutory payment bonds that meet the section's requirements. A bond that does not conform to 713.23 may be treated as a common law bond, and the statutory notice rules may not apply in the same way.
- The 45-day clock runs from first furnishing. Not from contract execution, not from a purchase order, not from delivery to the jobsite — the clock starts when the lienor first furnishes materials or services to the project.
- One-year limit on action against the bond. An action on the payment bond must be brought within one year (FLA. STAT. 713.23(1)(e)). This deadline is measured from the statutory trigger and cannot be casually extended.
- Strict construction against the lienor. Florida courts read the lien and bond statutes strictly against the party claiming the right. Defects that might be excused in other states are routinely fatal here.
- Identifying the correct bond and surety. The lienor must look to the specific bond recorded with the notice of commencement. Naming the wrong surety, or relying on a non-conforming bond document, undermines the claim before it begins.
What Is Included in the Download Package
The Florida Notice to Contractor download includes the fillable form prepared by the Deeds.com forms development team, completed-example pages illustrating typical entries, and a guide outlining the statutory framework, deadlines, and service requirements under FLA. STAT. 713.23. Files are delivered as instant downloads after checkout.
Important: Your property must be located in Washington County to use these forms. Documents should be recorded at the county recording office listed above.
This Notice to Contractor meets all recording requirements specific to Washington County.
Our Promise
The documents you receive here are guaranteed to meet or exceed the applicable Washington County recording format requirements. If there is a rejection caused by our formatting, we will correct the issue or refund your payment. This guarantee applies to document formatting only and does not extend to information entered by the user, the selection of the form, or the legal effect of the completed document.
Save Time and Money
Get your Washington County Notice to Contractor form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.
4.8 out of 5 - ( 4,804 Reviews )
Brenn C. 2 out of 5 stars
These products would be more useful if they final deed could be copied and pasted into a word document for proper formatting. Because most of the document is protected against selecting and copying, I did not find it useful. I would not purchase again.
Thank you for your feedback. We really appreciate it. Have a great day!
Christina H. 5 out of 5 stars
I appreciate having forms available and not having to go to a business supply or attorney. This is great. However, there are two individual quit claim deed forms and I don't know which one is appropriate.
Thank you for your feedback. We really appreciate it. Have a great day!
Jane C. 5 out of 5 stars
I wasn't sure what I was looking for initially so I printed out the wrong thing. Had to pay again to get the right one but much less expensive than getting it from a lawyer. Our military lawyers will make the forms official but they don't have the forms. Hope this makes things easier for our children when we pass. Thank you for offering this service.
Thank you for taking the time to leave your feedback. We have canceled and refunded the payment for your first order. We don't want you to pay for something you're not going to use. Have an amazing day.
Richard C. 5 out of 5 stars
Fast, effective, and good communication. I have no complaints at all.
Thank you for your positive words! We’re thrilled to hear about your experience.
James D. 5 out of 5 stars
I had a satisfying experience very informative and easy to navigate.
Thank you!
Jo Ann M. 5 out of 5 stars
Easy from the download to just fill out and print. Good instructions to follow. A cover letter form would be a extra plus
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Charles C. 5 out of 5 stars
I found this site to be very easy to use . I found and printed what I needed in just a few minutes after getting on the sit . Good work setting up this site . Thank you .
Thank you!
Kristen H. 5 out of 5 stars
This was such a money saver. I was told by someone at the courthouse that I had to have a lawyer prepare the paper work for my mom. They stated that family members couldn't prepare the papers. I was hopeful when I found that I could prepare the survivorship affidavit on Deeds. I was able to prepare everything myself and had no issues today when at the courthouse for all the changes. Thank you!
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
JOSEPH P. 3 out of 5 stars
It would have been a lot better if I could have downloaded ALL at once, as a package.
Thank you for your feedback. We really appreciate it. Have a great day!
Frank S. 5 out of 5 stars
ALL THE DEED DOCUMENTS ARE ALL EXCELLENT AND ADDITIONAL DOCUMENTS REGARDING COMPLETING THE DOCUMENTS!!! EXCELLENT!!
Your feedback is greatly appreciated. Thank you for taking the time to share your experience!
ANTHONY W. 5 out of 5 stars
It's been extremely easy to communicate across this platform.
Thank you!
William Q. 5 out of 5 stars
The website and information is fine. The proof in the pudding, of course, is whether the forms I used now will provide the results I want if the changes are challenged at some future date.
Thank you for your feedback. We really appreciate it. Have a great day!
Chad S. 5 out of 5 stars
GREAT SERVICE. A MUST HAVE FOR EVERY REAL ESTATE TRANSACTION!!THANK YOU FOR PROVIDING SUCH A CONVIENIENT EASY TO UNDERSTAND SERVICE.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Celestine U. 5 out of 5 stars
Very well done
Thank you!
Celeste F. 5 out of 5 stars
Great experience. No hassle. It kept me out of a government office.
Thank you for your feedback. We really appreciate it. Have a great day!