Saint Clair County Mechanics Lien (Claim of Lien) Form
Last validated November 3, 2026 by our Forms Development TeamFormatted for recording in Saint Clair County, for property anywhere in the county: rural and unincorporated areas as well as Algonac, Allenton, Anchorville, Avoca, Capac, Casco, Columbus, East China and 14 more.
- 3 documents included
- Immediate PDF download
- Formatting guarantee

Saint Clair County Mechanics Lien (Claim of Lien) Form
Fill in the blank Mechanics Lien (Claim of Lien) form formatted to comply with all Michigan recording and content requirements.

Saint Clair County Mechanics Lien (Claim of Lien) Guide
Line by line guide explaining every blank on the Mechanics Lien (Claim of Lien) form.

Saint Clair County Completed Example of the Mechanics Lien (Claim of Lien) Document
Example of a properly completed Michigan Mechanics Lien (Claim of Lien) document for reference.
All 3 documents above included • One-time purchase • No recurring fees
Immediate Download • Secure Checkout
Additional Michigan and Saint Clair County documents included at no extra charge:
Where to Record Your Documents
St. Clair County Register of Deeds
Port Huron, Michigan 48060
Hours: 8:00 to 12:00 & 1:00 to 4:30 Mon-Thu; 10:30 to 12:00 & 1:00 to 4:30 on Fri
Phone: (810) 989-6930
Recording Tips for Saint Clair County:
- Bring your driver's license or state-issued photo ID
- Ensure all signatures are in blue or black ink
- Ask about their eRecording option for future transactions
- Avoid the last business day of the month when possible
- Both spouses typically need to sign if property is jointly owned
Cities and Jurisdictions in Saint Clair County
Properties in any of these areas use Saint Clair County forms:
- Algonac
- Allenton
- Anchorville
- Avoca
- Capac
- Casco
- Columbus
- East China
- Emmett
- Fair Haven
- Fort Gratiot
- Goodells
- Harsens Island
- Jeddo
- Marine City
- Marysville
- Memphis
- North Street
- Port Huron
- Saint Clair
- Smiths Creek
- Yale
Hours, fees, requirements, and more for Saint Clair County
How do I get my forms?
Forms are available for immediate download after payment. The Saint Clair County forms will be in your account ready to download to your computer. An account is created for you during checkout if you don't have one. Forms are NOT emailed.
Are these forms guaranteed to be recordable in Saint Clair County?
Yes. Our form blanks are guaranteed to meet or exceed the applicable formatting requirements used for recording in Saint Clair County, including margin requirements, font requirements, and other layout standards. This guarantee applies to formatting, not to the legal sufficiency of information entered by the user or the suitability of a form for a particular transaction.
Can I reuse these forms?
Yes. You can reuse the forms for your personal use. For example, if you have multiple properties in Saint Clair County you only need to order once.
What do I need to use these forms?
The forms are PDFs that you fill out on your computer. The free Adobe Acrobat Reader is recommended, and most PDF apps also work. You do NOT enter your property information online - you download the blank forms and complete them privately on your own computer.
Are there any recurring fees?
No. This is a one-time purchase. Nothing to cancel, no memberships, no recurring fees.
How much does it cost to record in Saint Clair County?
Recording fees in Saint Clair County vary. Contact the recorder's office at (810) 989-6930 for current fees.
Questions answered? Let's get started!
Michigan counts a construction lien in days furnished, and then it stops counting. The right of a contractor, subcontractor, laborer, or supplier to a construction lien ceases to exist, MCL 570.1111(1) provides, unless a claim of lien is recorded within 90 days after that claimant's last furnishing of labor or material, with the register of deeds for each county where the improved real property is located. The lien came from the work; this recorded instrument, the one usually searched for as a Michigan mechanics lien, is what keeps that lien from lapsing.
A form the statute itself prints
Section 111 of the act, MCL 570.1111(2), provides that a claim of lien is to be in substantially the form it sets out, and this form follows that exemplar entry for entry: the lien claimant and address, the day labor or material was first provided, the legal description taken from the notice of commencement, the owner or lessee named in that same notice, the last day of providing labor or material, the contract amount including extras, the payment received, and the amount of the lien claimed. Pulling the description from the notice of commencement is what keeps the recorded claim and that notice pointing at one parcel, and MCL 570.1111(1) adds that a claim of lien is valid only as to property described in it and located in the recording county.
Three money entries, one calculation
The amount lines are not a demand figure. MCL 570.1107(1) caps a construction lien at the amount of the claimant's contract less payments made on the contract, so the contract amount including extras, the payment received, and the lien claimed sit on the face of the instrument in that order, and the third follows from the first two. The last furnishing date carries its own weight: Michigan reads the 90 days exactly, as the Supreme Court held in Northern Concrete Pipe, Inc v Sinacola Companies-Midwest, Inc, 461 Mich 316 (1999).
Recording is the middle of the sequence
MCL 570.1111(5) starts a second clock at the recording date: within 15 days, a copy of the claim of lien, with a copy of any proof of service recorded with it, goes to the designee named in the notice of commencement, personally or by certified mail with return receipt requested, and to the owner or lessee where no designee was named or the designee has died. Service by certified mail is complete on mailing. MCL 570.1112 makes the recording constructive notice, and MCL 570.1117(1) allows one year from that date for proceedings to enforce the lien and foreclose the interests subject to it.
Sworn, then recorded
The statutory exemplar closes with the words subscribed and sworn to before me, so the certificate here is a jurat rather than an acknowledgment, and the Michigan Law on Notarial Acts, MCL 55.261 to 55.315, supplies its content, including the county of commission and the county of the act under MCL 55.287. The page answers to MCL 565.201: a first line naming the recordable event, 2 1/2 inches clear at the top of page one, 10 point print in black ink on white paper, the signer's name printed beneath the signature, and the drafter's name and business address. MCL 600.2567(1)(a) sets the fee at $30.00 for a document regardless of page count.
How this claim of lien is set up
The form recites one lien claimant, with one signature block headed LIEN CLAIMANT and one jurat certificate for that signer, and it preprints no role, because a contractor, a subcontractor, a supplier, and a laborer all record under the same section. A subcontractor closing out a mechanical scope on a commercial building, a supplier whose final delivery fixed the last furnishing date, and a trade contractor left holding retainage each present the single claimant pattern this instrument recites, with the statutory laborer block left blank by a claimant who is not a laborer. Two shapes sit outside it: a claim prepared by an agent for several laborers under MCL 570.1111(6), and an assigned claim, which MCL 570.1111(3) has state that the construction lien having been assigned, the claim is made by the named assignee.
The package holds the fillable claim of lien form, a completed example filled out for an Oakland County commercial project, and a guide covering the statute, the entries, the jurat, and recording. The material is informational and is not legal advice.
Important: Your property must be located in Saint Clair County to use these forms. Documents should be recorded at the county recording office listed above.
This Mechanics Lien (Claim of Lien) meets all recording requirements specific to Saint Clair County.
Our Promise
The documents you receive here are guaranteed to meet or exceed the applicable Saint Clair County recording format requirements. If there is a rejection caused by our formatting, we will correct the issue or refund your payment. This guarantee applies to document formatting only and does not extend to information entered by the user, the selection of the form, or the legal effect of the completed document.
Save Time and Money
Get your Saint Clair County Mechanics Lien (Claim of Lien) form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.
4.8 out of 5 - ( 4,853 Reviews )
Paul R. 5 out of 5 stars
Worked very quickly and smoothly. Helps if you know what documents you need. Thanks.
Thank you for your feedback. We really appreciate it. Have a great day!
Seth T. 5 out of 5 stars
THE BEST WEBSITE I HAVE EVER SEEN FOR LEGAL DOCUMENTS!!! THANKS
Thanks Seth, we appreciate your feedback.
Roger G. 5 out of 5 stars
Straight to the point and easy to use site.
Thank you!
Charles C. 5 out of 5 stars
I found this site to be very easy to use . I found and printed what I needed in just a few minutes after getting on the sit . Good work setting up this site . Thank you .
Thank you!
Catherine W. 5 out of 5 stars
I appreciate your prompt and honest response. You did not find what I was looking for but You also did not charge Me. It was a pleasure working with You.
Thank you for your feedback Catherine, sorry we were unable to find what you needed. Have a wonderful day.
Daniel D. 5 out of 5 stars
quick and easy
Thank you Daniel.
Monica D. N. 5 out of 5 stars
The Web site is very intuitive, organized well and forms are easily found. The instructions provided are very helpful. Value in terms of price is very good.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Sandra W. 5 out of 5 stars
No issues with the forms.
Thank you!
Eric S. 5 out of 5 stars
Very easy and efficient to use. Thank you!
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Gjnana D. 5 out of 5 stars
These guidelines and form helped me lot in preparing quit deed to add my spouse's name in tittle property
Thank you for your feedback. We really appreciate it. Have a great day!
Michael S. 1 out of 5 stars
I'll give you a review. YOur deeds are way, way, TOO EXPENSIVE Michael Spinks, Attorney
Thank you for your feedback. We're sorry to hear that you're dissatisfied with our pricing.
We take pride in the quality of our products, and our prices reflect the costs involved in sourcing, producing, and ensuring the high standards we've set. It's a balancing act between affordability and maintaining these standards.
We're aware that everyone has a budget to consider, and we're constantly working on optimizing our pricing. However, we won't compromise the quality of our products for the sake of cutting costs. We believe in fair value, and we hope our customers do too.
Reida S. 5 out of 5 stars
Have used two times. Smooth transaction both times. Fast, simple and easy to use system. Would use them again in the future.
Thank you for your feedback. We really appreciate it. Have a great day!
Vickie M. 5 out of 5 stars
The website was easy to use even for me with little computer knowledge.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
April J. 5 out of 5 stars
The example and guide were invaluable! Easy to use and easy to fill out.
Thank you!
JD S. 5 out of 5 stars
I used Deeds.com recently. They were quick and got the job done quickly. Their online portal was extremely easy to use. I will definitely use them again.
Thank you!