Lake County Notice to Contractor Form
Last validated July 27, 2026 by our Forms Development Team
Lake County Notice to Contractor Form
Fill in the blank form formatted to comply with all recording and content requirements.

Lake County Notice to Contractor Guide
Line by line guide explaining every blank on the form.

Lake County Completed Example of the Notice to Contractor Document
Example of a properly completed form for reference.
All 3 documents above included • One-time purchase • No recurring fees
Immediate Download • Secure Checkout
Additional Florida and Lake County documents included at no extra charge:
Where to Record Your Documents
Public Records Center
Tavares, Florida 32778
Hours: 8:30 to 5:00 M-F
Phone: (352) 253-2600
South Lake Minneola Branch Office
Minneola, Florida
Hours: 8:30am to 12:00 & 1:00 to 4:30pm M-F
Phone: Same-day recording by 10:30am
North Lake Branch Office
The Villages of Lady Lake, Florida
Hours: 8:30am to 12:00 & 1:00 to 4:30pm M-F
Phone: Same-day recording by 9:30am
Recording Tips for Lake County:
- Check that your notary's commission hasn't expired
- Avoid the last business day of the month when possible
- Check margin requirements - usually 1-2 inches at top
- Leave recording info boxes blank - the office fills these
Cities and Jurisdictions in Lake County
Properties in any of these areas use Lake County forms:
- Altoona
- Astatula
- Astor
- Clermont
- Eustis
- Ferndale
- Fruitland Park
- Grand Island
- Groveland
- Howey In The Hills
- Lady Lake
- Leesburg
- Mascotte
- Minneola
- Montverde
- Mount Dora
- Okahumpka
- Paisley
- Sorrento
- Tavares
- Umatilla
- Yalaha
Hours, fees, requirements, and more for Lake County
How do I get my forms?
Forms are available for immediate download after payment. The Lake County forms will be in your account ready to download to your computer. An account is created for you during checkout if you don't have one. Forms are NOT emailed.
Are these forms guaranteed to be recordable in Lake County?
Yes. Our form blanks are guaranteed to meet or exceed the applicable formatting requirements used for recording in Lake County, including margin requirements, font requirements, and other layout standards. This guarantee applies to formatting, not to the legal sufficiency of information entered by the user or the suitability of a form for a particular transaction.
Can I reuse these forms?
Yes. You can reuse the forms for your personal use. For example, if you have multiple properties in Lake County you only need to order once.
What do I need to use these forms?
The forms are PDFs that you fill out on your computer. You'll need Adobe Reader (free software that most computers already have). You do NOT enter your property information online - you download the blank forms and complete them privately on your own computer.
Are there any recurring fees?
No. This is a one-time purchase. Nothing to cancel, no memberships, no recurring fees.
How much does it cost to record in Lake County?
Recording fees in Lake County vary. Contact the recorder's office at (352) 253-2600 for current fees.
Questions answered? Let's get started!
Florida's construction lien law splits payment-protection notices into two parallel tracks, and the Florida Notice to Contractor belongs to one of them. When a general contractor has furnished a statutory payment bond under FLA. STAT. 713.23 — recorded with the notice of commencement before work begins — a subcontractor or supplier not in direct contract with the general contractor cannot rely on the standard Notice to Owner. The bond replaces the property as the security for payment, and the document that perfects a claim against that bond is the Notice to Contractor. Sending the wrong notice, or sending the right notice late, eliminates the bond as a payment source.
What the Florida Notice to Contractor Does and When It Is Used
This notice tells the general contractor — and, in practice, the surety — that the lienor intends to look to the payment bond for protection on the work being supplied. It applies to private Florida construction projects where a 713.23 statutory payment bond has been recorded along with the notice of commencement. Material suppliers, sub-subcontractors, equipment lessors, and other lienors who are not contractually connected to the general contractor must serve this notice to preserve a claim. Laborers and parties in privity with the general contractor are excepted. Federal projects fall under the Miller Act and use a different mechanism entirely.
Statutory Requirements Under FLA. STAT. 713.23
The form identifies the parties and the project. At a minimum it names the owner who ordered the work, the general contractor coordinating the project, and the lienor furnishing labor or materials. It describes the real property where the improvement is being made and identifies the type of work or materials being supplied. The notice substantially follows the form set out in the statute (FLA. STAT. 713.23(1)(c)). Florida courts construe lien-law compliance strictly, and homemade variations risk being held insufficient.
The 45-Day Clock and Its Alternative
Timing is the trap that ends most bond claims. A lienor not in privity with the contractor — except a laborer — must serve the notice before beginning, or within 45 days after beginning, to furnish labor, materials, or supplies (FLA. STAT. 713.23(1)(c)). The clock runs from the first day of furnishing — not from the contract date and not from the purchase order.
An alternative window applies when the notice of commencement with the bond attached is not recorded before construction begins. In that situation, the lienor may serve the notice up to 45 days after being served with a copy of the bond (FLA. STAT. 713.23(1)(c)). A lienor who has not been provided a copy of the bond is entitled to demand one, and the statute imposes consequences on a party who refuses to furnish it.
Notice of Nonpayment — The Second Required Notice
The Notice to Contractor preserves the right to claim, but it is not the only notice the statute requires. Before bringing an action against the bond, the lienor must also serve a written notice of nonpayment on the contractor and the surety not later than 90 days after final furnishing of labor, services, or materials by the lienor (FLA. STAT. 713.23(1)(d)). The 90-day notice of nonpayment is a separate document with its own deadline; missing it eliminates the bond claim even when the initial Notice to Contractor was timely and correctly served.
How the Notice Must Be Served
Unlike many lien-related documents in Florida, the Notice to Contractor is served — not recorded with the county clerk. Service follows the methods authorized by FLA. STAT. 713.18: actual delivery to the person being served, or by common carrier delivery service or U.S. mail (registered, certified, or first-class with a certificate of mailing). Proof of service must be retained, because a bond claim that proceeds to litigation will turn on it.
Florida-Specific Traps
- Confusing the Notice to Contractor with the Notice to Owner. The Notice to Owner under FLA. STAT. 713.06 perfects a lien against real property on non-bonded jobs. The Notice to Contractor under 713.23 perfects a claim against a payment bond. They are not interchangeable, and using the wrong one on a bonded job is fatal to the claim.
- Statutory bond versus common law bond. Section 713.23 governs statutory payment bonds that meet the section's requirements. A bond that does not conform to 713.23 may be treated as a common law bond, and the statutory notice rules may not apply in the same way.
- The 45-day clock runs from first furnishing. Not from contract execution, not from a purchase order, not from delivery to the jobsite — the clock starts when the lienor first furnishes materials or services to the project.
- One-year limit on action against the bond. An action on the payment bond must be brought within one year (FLA. STAT. 713.23(1)(e)). This deadline is measured from the statutory trigger and cannot be casually extended.
- Strict construction against the lienor. Florida courts read the lien and bond statutes strictly against the party claiming the right. Defects that might be excused in other states are routinely fatal here.
- Identifying the correct bond and surety. The lienor must look to the specific bond recorded with the notice of commencement. Naming the wrong surety, or relying on a non-conforming bond document, undermines the claim before it begins.
What Is Included in the Download Package
The Florida Notice to Contractor download includes the fillable form prepared by the Deeds.com forms development team, completed-example pages illustrating typical entries, and a guide outlining the statutory framework, deadlines, and service requirements under FLA. STAT. 713.23. Files are delivered as instant downloads after checkout.
Important: Your property must be located in Lake County to use these forms. Documents should be recorded at the office below.
This Notice to Contractor meets all recording requirements specific to Lake County.
Our Promise
The documents you receive here are guaranteed to meet or exceed the applicable Lake County recording format requirements. If there is a rejection caused by our formatting, we will correct the issue or refund your payment. This guarantee applies to document formatting only and does not extend to information entered by the user, the selection of the form, or the legal effect of the completed document.
Save Time and Money
Get your Lake County Notice to Contractor form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.
4.8 out of 5 - ( 4771 Reviews )
Patricia C.
February 6th, 2020
They had exactly what I was looking for. Easy to follow instructions and very helpful.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Joni Y.
November 25th, 2019
Deeds.com is a very up to date & easy instruction website. I recommend this site to all who are looking for forms dealing with deeds. Thank you for making life easy in this aspect.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
dorothy f.
March 27th, 2019
Thank you, for help.
Anytime Dorothy, have a great day.
JoAnn S.
July 31st, 2021
Easy to process orders.
Thank you!
Jacque G.
December 18th, 2019
Very helpful and easy to access.
Thank you!
Charles S.
February 14th, 2025
very happy with guidance and responses - thank you - not finished yet but confident
We are sincerely grateful for your feedback and are committed to providing the highest quality service. Thank you for your trust in us.
Alan C.
December 10th, 2020
I thought the instructions could have been a little better. I didn't know how to do this if the spouses are married but living in separate residences. Also I didn't understand the "Prior Instrument Reference". That should be explained better. Very sketchy instructions.
Thank you for your feedback. We really appreciate it. Have a great day!
Judith F.
June 29th, 2022
Was easy to use the eRecording service.
Thank you!
MIchael T.
March 23rd, 2023
very helpful in a trouble free manner.
Thank you!
Ellen D.
November 25th, 2019
Fantastic service! The forms were available to download instantly and they were perfect for my situation. Easy to use on my older computer. Thanks!
Thank you for your feedback. We really appreciate it. Have a great day!
Mica M.
September 25th, 2020
Best Way EVER to record a warranty deed! It was nice to not have to drive anywhere and find the facility closed or "unable to process due to covid19 and buildings being closed". The correspondence between me and deeds.com was very timely in our back and forth email correspondence, and the processing was all finished in a timely manner. Totally worth the extra $15 that I paid in addition to the recording fee. I would use this again and again. My time and the efficiency of the job completed is worth the money.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Linda E.
August 22nd, 2019
Forms were perfect, guide was very helpful. Passed recording official's scrutiny with flying colors. Will be back should the need arise.
Thank you!
Maria H.
September 18th, 2020
Great job. Helped me through some technical difficulties and got it done!
Thank you for your feedback. We really appreciate it. Have a great day!
Jennifer H.
October 12th, 2020
Deeds.com is amazing. It made finding out how to file legal documents worry free and easily understood. Thank You
Thank you for your feedback. We really appreciate it. Have a great day!
John G.
August 6th, 2019
Great on line help with the recording process!
We appreciate your business and value your feedback. Thank you. Have a wonderful day!