Centre County Claim of Mechanics Lien Guide
Line by line guide explaining every blank on the form.

Centre County Completed Example of the Claim of Mechanics Lien Document
Example of a properly completed form for reference.
All 3 documents above included • One-time purchase • No recurring fees
Immediate Download • Secure Checkout
Additional Pennsylvania and Centre County documents included at no extra charge:
Where to Record Your Documents
Recorder of Deeds - County Office Building
Bellefonte, Pennsylvania 16823-1488
Hours: 8:30 to 5:00 M-F
Phone: (814) 355-6801
Recording Tips for Centre County:
- Ensure all signatures are in blue or black ink
- Verify all names are spelled correctly before recording
- Ask about their eRecording option for future transactions
- Recording fees may differ from what's posted online - verify current rates
- Have the property address and parcel number ready
Cities and Jurisdictions in Centre County
Properties in any of these areas use Centre County forms:
- Aaronsburg
- Bellefonte
- Blanchard
- Boalsburg
- Centre Hall
- Clarence
- Coburn
- Fleming
- Howard
- Julian
- Lemont
- Madisonburg
- Milesburg
- Millheim
- Mingoville
- Moshannon
- Orviston
- Pennsylvania Furnace
- Philipsburg
- Pine Grove Mills
- Port Matilda
- Rebersburg
- Sandy Ridge
- Snow Shoe
- Spring Mills
- State College
- University Park
- Woodward
Hours, fees, requirements, and more for Centre County
How do I get my forms?
Forms are available for immediate download after payment. The Centre County forms will be in your account ready to download to your computer. An account is created for you during checkout if you don't have one. Forms are NOT emailed.
Are these forms guaranteed to be recordable in Centre County?
Yes. Our form blanks are guaranteed to meet or exceed the applicable formatting requirements used for recording in Centre County, including margin requirements, font requirements, and other layout standards. This guarantee applies to formatting, not to the legal sufficiency of information entered by the user or the suitability of a form for a particular transaction.
Can I reuse these forms?
Yes. You can reuse the forms for your personal use. For example, if you have multiple properties in Centre County you only need to order once.
What do I need to use these forms?
The forms are PDFs that you fill out on your computer. You'll need Adobe Reader (free software that most computers already have). You do NOT enter your property information online - you download the blank forms and complete them privately on your own computer.
Are there any recurring fees?
No. This is a one-time purchase. Nothing to cancel, no memberships, no recurring fees.
How much does it cost to record in Centre County?
Recording fees in Centre County vary. Contact the recorder's office at (814) 355-6801 for current fees.
Questions answered? Let's get started!
Obtaining a mechanic's lien in Pennsylvania
Mechanic's Liens are governed by Title 49 of the Pennsylvania Consolidated Statutes.
A mechanic's lien is a type of security interest used to guarantee payment for work completed or materials delivered in connection with a construction contract. You might be familiar with other types of liens such as a judgment lien or tax lien. A mechanic's lien works the same way by attaching itself to the title (ownership) interest of the property and making it difficult for the owner to sell or refinance without first resolving the lien. Therefore, it's a powerful tool when it's used properly.
In Pennsylvania, the procedure for obtaining and enforcing a mechanic's lien is governed under the Mechanic's Lien Law of 1963 (49 P.S. 1101). Liens are available to general contractors, subcontractors, laborers, and material or equipment suppliers who meet the requirements for filing including sending the necessary notices of commencement and furnishing as well as the preliminary (pre-lien) notice.
A lien can be claimed for unpaid labor or materials provided for the construction, alteration, or repair that exceeds a value of $500.00 (301). The lien must reflect only the actual costs of labor or materials as well as lost profits and overhead. You cannot include items such as delay or impact damages from breach of the contract (although you may recover these in a separate lawsuit on the underlying contract).
The lien must also be filed no later than six (6) months after the lien claimant has completed work (502(a)(1)). Be sure to check the filing requirements for the clerk of courts in the county in which the property is located. You may be required to attach a cover sheet or additional documentation. Review the requirements by visiting the local court's website.
The claim for lien must include the following: (1) The name of the party claimant, and whether he files as contractor or subcontractor; (2) the name and address of the owner (or reputed owner); (3) the date on which the claimant completed its work; (4) if the claimant is a subcontractor, the name of the person with whom the claimant contracted, and the date on which the formal notice of intention to file (if required) was given; (5) if the claimant is a general contractor under a contract or contracts for an agreed sum, an identification of the contract and a general statement of the kind and character of the labor or materials furnished; (6) if the claimant is either a subcontractor or a general contractor who is not under a contract for an agreed sum, a detailed statement of the kind and character of the labor and/or materials furnished and of the prices charged for each of them; (7) the amount or sum claimed to be due; and (8) a description of the improvement and of the property claimed to be subject to the lien, as reasonably necessary to identify them. (503)
After filing, the claimant must serve the lien on the owner. Service is a necessary part of due process that allows the owner to receive notice of the pending action and an opportunity to contest it. The traditional method for serving liens in Pennsylvania is by sheriff's service, although private process servers may also be employed. Not later than twenty (20) days after the lien claim has been served upon an owner or (where applicable) posted upon the improvement, the lien claimant must file with the prothonotary (clerk of courts) either an affidavit of service or a document signed by the owner accepting service (502(a)(2)).
Once you have your lien in place, you must sue to foreclose on the lien if the owner (or reputed owner) still hasn't paid. An action to obtain judgment upon a claim filed shall be commenced within two (2) years from the date of filing unless the time be extended in writing by the owner (701(b)).
At any time after the completion of the work by a subcontractor, any owner or contractor may file a document with the court called a "rule" which orders the lien claimant to file lawsuit foreclosing on the lien within twenty (20) days of the rules service on the claimant (506(a)). If the claimant fails to file suit within that time, the lien is declared invalid.
This article is provided for informational purposes only and does not constitute legal advice. Contact an attorney with questions about the Claim of Lien, or with any other issues related to mechanic's liens in Pennsylvania.
Important: Your property must be located in Centre County to use these forms. Documents should be recorded at the office below.
This Claim of Mechanics Lien meets all recording requirements specific to Centre County.
Our Promise
The documents you receive here are guaranteed to meet or exceed the applicable Centre County recording format requirements. If there is a rejection caused by our formatting, we will correct the issue or refund your payment. This guarantee applies to document formatting only and does not extend to information entered by the user, the selection of the form, or the legal effect of the completed document.
Save Time and Money
Get your Centre County Claim of Mechanics Lien form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.
4.8 out of 5 - ( 4693 Reviews )
Bill M.
September 21st, 2022
I found the path from the home page to actually ordering the document I wanted extremely convoluted and non-intuitive. I went around in circles several times before I figured out how to actually buy the document.
Thank you for your feedback. We really appreciate it. Have a great day!
Michael T.
July 6th, 2020
Quick, simple and easy.
Thank you!
Patricia S.
August 3rd, 2022
The forms was easy to use and the guides was helpful
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Nancy H.
December 31st, 2018
Site was excellent and saved a trip to the County office to pick up forms.
Thank you Nancy. Glad we could help. Have a great day!
Ann M.
February 11th, 2022
I was extremely pleased with how easy this process was, and how quickly my document was recorded. I will definitely use this again!
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Michael F.
November 6th, 2025
Very helpful and easy to use.
We deeply appreciate the trust you have placed in our services. Thank you for your valuable feedback and for choosing us.
jerry k.
May 27th, 2021
very easy to download, works great
Thank you for your feedback. We really appreciate it. Have a great day!
Rahul P.
July 19th, 2023
Excellent Site for recording documents to respective county Recorder Office. Excellent customer service, very well informed and experienced staff who responds promptly and guide customers throughout recording process. My recording was suspended But KVH (Staff) gave me proper timely advise and guided me for the procedure till recording was done by county office. I would like to give 6 stars or more to the site as per my experience with this site. Highly recommended site
Thank you for your feedback. We really appreciate it. Have a great day!
Mallah B.
October 7th, 2021
I think this company offers a great service that is non-discriminatory and allows me to save time going downtown and hassle dealing with different personalities.
Thank you for your feedback. We really appreciate it. Have a great day!
Sara M.
February 4th, 2025
This makes work so much easier now that I don't have to drive to each county to record. Thank you.
It was a pleasure serving you. Thank you for the positive feedback!
John H.
August 1st, 2019
Great service
Thank you!
Carol R.
February 19th, 2023
I found the site to be useful,informative and very accessable. Thank You
Thank you!
Christina W.
September 4th, 2019
I stand corrected. I received my report and it was exactly what I requested.
Thank you!
Rachel F.
February 18th, 2019
Easy and can add our own additional language in spaces provided. Thank you!
Thank you Rachel!
Thomas W.
January 16th, 2019
easy to use, no problems except in beneficiary box. Need to make the box bigger because I have 4 beneficiaries to list. how do I enlarge the box.
Thanks for reaching out. All available space on the document is being used. As is noted in the guide, if you have information that does not fit in the available space the included exhibit page should be used.