Pierce County Notice to Construction Lender Guide

Pierce County Notice to Construction Lender Guide

Line by line guide explaining every blank on the form.

Document Last Validated 4/8/2026
Pierce County Completed Example of the Notice to Construction Lender Document

Pierce County Completed Example of the Notice to Construction Lender Document

Example of a properly completed form for reference.

Document Last Validated 5/11/2026

All 3 documents above included • One-time purchase • No recurring fees

Immediate Download • Secure Checkout

Important: Your property must be located in Pierce County to use these forms. Documents should be recorded at the office below.

Where to Record Your Documents

Pierce County Auditor

Address:
2401 S 35th St, Rm 200
Tacoma, Washington 98409

Hours: 8:30 to 4:30 Mon through Fri

Phone: 253.798.7440

Recording Tips for Pierce County:
  • Ensure all signatures are in blue or black ink
  • Double-check legal descriptions match your existing deed
  • White-out or correction fluid may cause rejection
  • Recording fees may differ from what's posted online - verify current rates

Cities and Jurisdictions in Pierce County

Properties in any of these areas use Pierce County forms:

  • Anderson Island
  • Ashford
  • Bonney Lake
  • Buckley
  • Camp Murray
  • Carbonado
  • Dupont
  • Eatonville
  • Elbe
  • Fox Island
  • Gig Harbor
  • Graham
  • Kapowsin
  • La Grande
  • Lakebay
  • Lakewood
  • Longbranch
  • Longmire
  • Mcchord Afb
  • Mckenna
  • Milton
  • Orting
  • Paradise Inn
  • Puyallup
  • Roy
  • South Prairie
  • Spanaway
  • Steilacoom
  • Sumner
  • Tacoma
  • University Place
  • Vaughn
  • Wauna
  • Wilkeson

View Complete Recorder Office Guide

Hours, fees, requirements, and more for Pierce County

How do I get my forms?

Forms are available for immediate download after payment. The Pierce County forms will be in your account ready to download to your computer. An account is created for you during checkout if you don't have one. Forms are NOT emailed.

Are these forms guaranteed to be recordable in Pierce County?

Yes. Our form blanks are guaranteed to meet or exceed the applicable formatting requirements used for recording in Pierce County, including margin requirements, font requirements, and other layout standards. This guarantee applies to formatting, not to the legal sufficiency of information entered by the user or the suitability of a form for a particular transaction.

Can I reuse these forms?

Yes. You can reuse the forms for your personal use. For example, if you have multiple properties in Pierce County you only need to order once.

What do I need to use these forms?

The forms are PDFs that you fill out on your computer. You'll need Adobe Reader (free software that most computers already have). You do NOT enter your property information online - you download the blank forms and complete them privately on your own computer.

Are there any recurring fees?

No. This is a one-time purchase. Nothing to cancel, no memberships, no recurring fees.

How much does it cost to record in Pierce County?

Recording fees in Pierce County vary. Contact the recorder's office at 253.798.7440 for current fees.

Questions answered? Let's get started!

Getting a Construction Lender to Withhold Funds

As part of the construction lien process, you might find it useful to send a notice to the construction lender ordering the lender to withhold distribution of funds from the loan proceeds until you are paid. This is another potential weapon in the lien claimant's arsenal. In some states, this notice is called as a "stop notice" because it instructions the lender to stop payment. The notice can be used as a first step or as an alternative to securing a mechanic's lien.

Any potential lien claimant who has not received a payment within five days after the date required by their contract, invoice, employee benefit plan agreement, or purchase order may give a notice to a construction lender within thirty-five days of the date required for payment of the contract, invoice, employee benefit plan agreement, or purchase order. See R.C.W. 60.04.221(1).

The notice must be signed by the potential lien claimant or some person authorized to act on his or her behalf. R.C.W. 60.04.221(2). The notice must be provided in writing to the lender at the office administering the construction financing, along with a copy given to the owner and the appropriate prime contractor. R.C.W. 60.04.221(3).

Two methods can be used to serve the notice: (1) mailing the notice by certified or registered mail to the lender, owner, and appropriate prime contractor; or (2) delivering or serving the notice personally and obtaining evidence of delivery in the form of a receipt or other acknowledgment signed by the lender, owner, and appropriate prime contractor, or an affidavit of service. Id.

The notice must include the following information: (1) the name of the person, firm, trustee, or corporation filing the notice, (2) the name of the prime contractor, common law agent, or construction agent ordering the same, (3) a common or street address of the real property being improved or the legal description of the real property, and (4) the name, business address, and telephone number of the lien claimant. R.C.W. 60.04.221(4).

After the lender receives a copy of the notice, the lender must then withhold from the next and subsequent draws the amount claimed to be due as stated in the notice. R.C.W. 60.04.221(5). Alternatively, the lender may obtain from the prime contractor or borrower a payment bond for the benefit of the potential lien claimant in an amount sufficient to cover the amount stated in the potential lien claimant's notice. Id. The lender is obligated to withhold amounts only to the extent that sufficient interim or construction financing funds remain undisbursed as of the date the lender receives the notice. Id.

Once the notice is received by the lender, sums that are withheld shall not be disbursed by the lender, except by the written agreement of the potential lien claimant, owner, and prime contractor, or court order. R.C.W. 60.04.221(6).

If the lender fails to abide by the terms of the notice, then the mortgage, deed of trust, or other encumbrance securing the lender will be made secondary to the lien of the potential lien claimant to the extent of the interim or construction financing wrongfully disbursed, but in no event more than the amount stated in the notice plus costs as fixed by the court, including reasonable attorneys' fees. R.C.W. 60.04.221(7).

Use caution in drafting the notice to the lender and ensure the form is accurate. If there are mistakes, any potential lien claimant will be liable for any loss, cost, or expense, including reasonable attorneys' fees and statutory costs, to a party injured thereby arising out of any unjust, excessive, or premature notice that is filed. R.C.W. 60.04.221(8).

This article is provided for informational purposes only and should not be relied upon as a substitute for the advice of an attorney. If you have any questions about the notice to lender document or any other issues related to liens, please consult with a Washington attorney.

Important: Your property must be located in Pierce County to use these forms. Documents should be recorded at the office below.

This Mechanics Lien Notice to Construction Lender meets all recording requirements specific to Pierce County.

Our Promise

The documents you receive here are guaranteed to meet or exceed the applicable Pierce County recording format requirements. If there is a rejection caused by our formatting, we will correct the issue or refund your payment. This guarantee applies to document formatting only and does not extend to information entered by the user, the selection of the form, or the legal effect of the completed document.

Save Time and Money

Get your Pierce County Mechanics Lien Notice to Construction Lender form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.

4.8 out of 5 - ( 4727 Reviews )

David J.

November 12th, 2019

Excellent documents, downloaded quick, completed and printed with no problems. Thank you

Reply from Staff

Thank you!

barbara s.

June 3rd, 2020

I was in a rush to record a quit claim deed, however due to covid 19 Miami dade county recorders office are not open to public. According to staff I would have to mail in the quit claim deed and wait approximately two weeks for the deed to get recorded. Thanks to Deeds.com I got my document recorded in less than one day. You guys are awesome, I will use this company anytime I need something like this again. Very reliable.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Gary M.

February 13th, 2024

This was such an easy experience

Reply from Staff

We are grateful for your feedback and looking forward to serving you again. Thank you!

Benjamin D.

June 30th, 2020

THANK YOU. Your materials are excellent and provided the information and guidance requested and needed.

Reply from Staff

Thank you!

Cynthia S.

April 6th, 2021

Great service got everything I needed with a click of a tab. Thank You...

Reply from Staff

Thank you for your feedback. We really appreciate it. Have a great day!

Tiqula D.

July 14th, 2021

Deeds.com is beyond convenient! It's a wonderful service for all your recording needs. The service is beyond fast and professional. Easy as 1 2 3....

Reply from Staff

Thank you for your feedback. We really appreciate it. Have a great day!

Debby P.

April 2nd, 2020

First time user and the service was great.. I typically go to recording kiosk at the libraries. This was fast and easy.. I appreciate the great service

Reply from Staff

Thank you for your feedback. We really appreciate it. Have a great day!

Linda M L.

September 7th, 2023

Easy to use, documents look good, but pretty expensive.

Reply from Staff

Thank you for your feedback. We really appreciate it. Have a great day!

Leslie S.

February 12th, 2020

The site was quick and easy to find information I needed. It also provided extra paperwork that would assist me.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Michael M.

April 17th, 2024

Great service that satisfied all my needs. Great prices too.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Robert R.

August 26th, 2025

Big savings and easy to use. Thanks so much.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Harry S.

March 30th, 2021

This is my first time using the service. Wow! How efficient and effortless! Keep up the good work!

Reply from Staff

Thank you!

Miranda C.

August 16th, 2023

very expensive

Reply from Staff

Thank you for your continued trust and repeated purchases with us over the past year. We deeply value our loyal customers and understand the importance of providing value for your investment. Our pricing reflects the meticulous care, research, and expertise we put into each of our legal forms. However, we always strive to improve and genuinely value your feedback.

Jacqueline S.

May 4th, 2021

Outstanding service. The quit claim Deed form was great. Very easy to use and explained very clearly. Definitely recommend.

Reply from Staff

Thank you for your feedback. We really appreciate it. Have a great day!

Jerry E.

January 21st, 2022

7 stars!

Reply from Staff

Thank you!