Monroe County Conditional Waiver and Release of Lien upon Final Payment Form
Last validated May 14, 2026 by our Forms Development Team
Monroe County Conditional Waiver and Release of Lien upon Final Payment Form
Fill in the blank form formatted to comply with all recording and content requirements.

Monroe County Conditional Waiver and Release of Lien upon Final Payment Guide
Line by line guide explaining every blank on the form.

Monroe County Completed Example of the Conditional Waiver and Release of Lien upon Final Payment Document
Example of a properly completed form for reference.
All 3 documents above included • One-time purchase • No recurring fees
Immediate Download • Secure Checkout
Additional Florida and Monroe County documents included at no extra charge:
Where to Record Your Documents
Clerk of the Court - Key West
Key West, Florida 33040
Hours: 8:30 to 5:00 M-F
Phone: (305) 294-4641
Marathon Office
Marathon, Florida 33050
Hours: 8:30 to 5:00 M-F
Phone: (305) 292-3540
Plantation Key Office 1
Plantation Key, Florida 33070
Hours: 8:30 to 5:00 M-F
Phone: (305) 852-7145
Plantation Key Office 2
Plantation Key, Florida 33070
Hours: 8:30 to 5:00 M-F
Phone: (305) 852-7145
Recording Tips for Monroe County:
- Bring your driver's license or state-issued photo ID
- Make copies of your documents before recording - keep originals safe
- Multi-page documents may require additional fees per page
Cities and Jurisdictions in Monroe County
Properties in any of these areas use Monroe County forms:
- Big Pine Key
- Islamorada
- Key Colony Beach
- Key Largo
- Key West
- Long Key
- Marathon
- Marathon Shores
- Summerland Key
- Tavernier
Hours, fees, requirements, and more for Monroe County
How do I get my forms?
Forms are available for immediate download after payment. The Monroe County forms will be in your account ready to download to your computer. An account is created for you during checkout if you don't have one. Forms are NOT emailed.
Are these forms guaranteed to be recordable in Monroe County?
Yes. Our form blanks are guaranteed to meet or exceed the applicable formatting requirements used for recording in Monroe County, including margin requirements, font requirements, and other layout standards. This guarantee applies to formatting, not to the legal sufficiency of information entered by the user or the suitability of a form for a particular transaction.
Can I reuse these forms?
Yes. You can reuse the forms for your personal use. For example, if you have multiple properties in Monroe County you only need to order once.
What do I need to use these forms?
The forms are PDFs that you fill out on your computer. You'll need Adobe Reader (free software that most computers already have). You do NOT enter your property information online - you download the blank forms and complete them privately on your own computer.
Are there any recurring fees?
No. This is a one-time purchase. Nothing to cancel, no memberships, no recurring fees.
How much does it cost to record in Monroe County?
Recording fees in Monroe County vary. Contact the recorder's office at (305) 294-4641 for current fees.
Questions answered? Let's get started!
Lien waivers or releases are used to surrender the right to a lien, either in full or in part depending on the type of lien release form selected. Florida's Construction Lien Law authorizes statutory waivers at 713.20 Fla. Stat. (2016).
Under 713.20(5), lienors may waive, on condition
The Florida Conditional Waiver and Release of Lien upon Final Payment is the closeout counterpart to the conditional progress waiver in section 713.20 of the Florida Statutes — total in scope, but conditioned on the final payment actually clearing. Where the unconditional final waiver releases all remaining lien rights immediately on signing regardless of whether the lienor is paid, the conditional final version keeps the lienor protected until the funds are actually in the account. Florida is one of the few states to legislate this kind of scenario-specific waiver wording, and the conditional final waiver exists for the closeout situation that comes up on most jobs: the lienor needs to deliver a final release in exchange for the final draw, but the check is being handed over at settlement rather than after the funds clear.
What the Florida Conditional Waiver and Release of Lien upon Final Payment Does
This form is signed by a lienor at project close to release all remaining lien rights against the property, with the release becoming effective only when the final payment is actually received and clears. "Conditional" assigns the credit risk of the payment to the customer or owner; "final" makes the waiver total in scope rather than tied to a single progress billing. The most common use is at the closing of a final draw or settlement disbursement — the lienor signs the conditional final waiver to provide closing parties with documentation of intent to release, while preserving lien rights as a backstop until the wire or check actually settles.
Florida Statutory Requirements Under Section 713.20
Florida codifies four statutory lien waiver forms in section 713.20 — conditional or unconditional, paired with progress or final payment — and requires that any waiver "substantially follow" the statutory wording for the matching scenario. The statute supplies the conditional language that makes the release contingent on payment, and the final language that makes the release total. Mixing scenarios, deleting required fields, or rewriting the conditional clause can convert the document into something other than a section 713.20 conditional final waiver. Title companies, construction lenders, and counsel reviewing closeout files typically check the wording against the statute precisely because the four forms are not interchangeable.
The form must identify the lienor, the customer, the property owner, the amount of the conditional final payment, and the property — typically by parcel identifier and legal description (§ 713.20).
Execution: No Witnesses, No Notary Required
Section 713.20 statutory waivers do not require witnesses or notarization to be effective. The lienor signs and dates the form. As with the unconditional final waiver, construction lenders and title insurers handling closing on a completed project may insist on notarized closeout waivers as a matter of internal underwriting policy. Notarization is not a statutory prerequisite, but it is often a practical one when the document is being delivered into a closing.
Florida-Specific Traps
The conditional final waiver shares some traps with the conditional progress waiver and others with the unconditional final waiver, and adds a few of its own:
- Advance waivers are void. Lien rights for labor, services, or materials not yet furnished cannot be released in advance under Florida law (§ 713.20).
- The condition is automatic and absolute. Until the final payment is actually received and clears, no lien rights are released. If the wire fails or the check is dishonored, the lienor's chapter 713 rights remain intact.
- Banks and title companies often will not rely on it. Because the release is contingent on payment clearance, a conditional final waiver does not give the closing parties documented proof that lien rights have been extinguished. Title underwriters issuing policies free of construction lien exceptions, and lenders authorizing final disbursement on the construction loan, frequently require the unconditional version and treat the conditional final waiver as a placeholder until the payment clears.
- Retainage and final draw mismatches. The "final payment" recited on the form should be the actual final payment, including any retainage being released. A waiver that recites the wrong amount, or that is signed against a payment that does not include retainage everyone assumes is being closed out, can leave a portion of the lienor's exposure outside the scope of the release.
- Punch list and warranty work. Once payment clears, the conditional final waiver releases all remaining lien rights — including for any unbilled corrective work the lienor has performed. As with the unconditional version, the lienor should make sure that all extras, change orders, and stored materials are billed and accounted for in the final payment amount before signing.
- "Substantially follow" still applies. A non-conforming conditional final waiver may not be enforceable as a section 713.20 waiver, which is the worst possible outcome at closeout — the lienor may have given up nothing, and the closing parties may have received a document that does not deliver what they thought it did.
- Notice of Commencement and Notice of Termination alignment. The property described in the waiver should match the property described in the Notice of Commencement (§ 713.13), and lienors closing out near the recording of a Notice of Termination (§ 713.132) should confirm their post-termination work is fully billed before signing.
- Two-step closings. On many Florida projects, a conditional final waiver is delivered into closing to provide intent-to-release documentation, and the lienor then issues an unconditional final waiver after the funds clear. Lienors should understand whether they are delivering only the conditional waiver, only the unconditional version, or both — and at what stage — so that the correct document carries the correct risk allocation.
How the Waiver Is Used
The conditional final waiver is not recorded in the county's official records. It is delivered to the owner, general contractor, construction lender, or title company at the final draw or settlement, and is retained with the closing file. Closing parties typically pair it with bank confirmation that the underlying payment has cleared, at which point the conditional final waiver functions as the lienor's complete release. On jobs where the closing parties require an unconditional final waiver to issue title insurance or fund the final disbursement, the conditional version is often delivered first as evidence of intent and then replaced with the unconditional form once the payment is settled.
Download Package
The download package includes the Florida Conditional Waiver and Release of Lien upon Final Payment, drafted to follow the statutory wording at section 713.20, a completed example showing how each field is filled in, and a guide explaining the form's role at closeout, the conditional structure, and how it fits with the other three section 713.20 waiver scenarios. The forms are prepared by Deeds.com's forms development team and are delivered as instant downloads.
of payment, a lien they already filed against the owner's interest in the improved property. The release contains information about the lienor, the customer, the property owner, the property description, the payment amount, and a date to finalize the work covered by the waiver.
Each case is unique, so contact an attorney with specific questions on lien waivers or any other issues related to Florida Construction Liens.
Important: Your property must be located in Monroe County to use these forms. Documents should be recorded at the office below.
This Conditional Waiver and Release of Lien upon Final Payment meets all recording requirements specific to Monroe County.
Our Promise
The documents you receive here are guaranteed to meet or exceed the applicable Monroe County recording format requirements. If there is a rejection caused by our formatting, we will correct the issue or refund your payment. This guarantee applies to document formatting only and does not extend to information entered by the user, the selection of the form, or the legal effect of the completed document.
Save Time and Money
Get your Monroe County Conditional Waiver and Release of Lien upon Final Payment form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.
4.8 out of 5 - ( 4726 Reviews )
RONDA S.
March 18th, 2021
I just love this site!
Thank you!
DARLA L.
September 8th, 2022
I was happy with the quick response to obtain the requested forms. Effective and easy website to use.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Scott W.
April 8th, 2024
Finding and downloading necessary forms, and especially the example forms, were tremendously easy and trouble free, and the fact the forms were updated recently was a big selling point. If other forms are needed, this is were I'm coming.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Evelyn T.
March 26th, 2025
Easy to follow; user friendly.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
David M.
July 6th, 2020
Best $20 ever spent. I'm a bit of an idiot with these things, thankfully there are professionals who know what they are doing so I don't screw things up...
Thank you!
Jay R.
December 1st, 2020
First time user. Great service, a little costly though
Thank you!
Susan T.
January 21st, 2019
This was perfect for my county I will be recommending your forms to all my clients thank you.
Thank you Susan, have a great day!
Kevin M.
May 13th, 2020
Maricopa County Recorders office directed to use Deeds.com for all forms, etc. Easily found the Warranty Deed form, instructions & sample form I was looking for.
Thank you!
Michael K.
April 2nd, 2021
I haven't used them yet. So far so good.
Thank you!
Katherine A R.
March 8th, 2023
It's very easy to navigate through the website to find the service that you want. Great program.
Thank you!
DAVID K.
May 15th, 2020
You are definitely the place to go for forms and other things which I need to solve my problems. Thanks for your help.
Thank you!
John M.
August 18th, 2022
I ordered my gift deed forms one evening, filled them out the next day, and registered them with the register of deeds the next morning. Boom. Done! Easy peasy, no lawyer expense!
Thank you!
David A.
May 3rd, 2022
Forms were just what I needed. Very well explained and easy to use.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Ming Z.
September 28th, 2022
Definitely 5 Stars !
Thank you!
A R M.
May 1st, 2021
Great so far. Just downloaded all the documents, and they seem to be easy to save and are fillable. A R M
Thank you for your feedback. We really appreciate it. Have a great day!