Monroe County Conditional Waiver and Release of Lien upon Progress Payment Guide

Monroe County Conditional Waiver and Release of Lien upon Progress Payment Guide

Line by line guide explaining every blank on the form.

Document Last Validated 4/27/2026
Monroe County Completed Example of the Conditional Waiver and Release of Lien upon Progress Payment Form

Monroe County Completed Example of the Conditional Waiver and Release of Lien upon Progress Payment Form

Example of a properly completed form for reference.

Document Last Validated 3/31/2026

All 3 documents above included • One-time purchase • No recurring fees

Immediate Download • Secure Checkout

Important: Your property must be located in Monroe County to use these forms. Documents should be recorded at the office below.

Where to Record Your Documents

Clerk of the Court - Key West

Address:
500 Whitehead St
Key West, Florida 33040

Hours: 8:30 to 5:00 M-F

Phone: (305) 294-4641

Marathon Office

Address:
3117 Overseas Highway
Marathon, Florida 33050

Hours: 8:30 to 5:00 M-F

Phone: (305) 292-3540

Plantation Key Office 1

Address:
88820 Overseas Highway
Plantation Key, Florida 33070

Hours: 8:30 to 5:00 M-F

Phone: (305) 852-7145

Plantation Key Office 2

Address:
50 High Point Rd
Plantation Key, Florida 33070

Hours: 8:30 to 5:00 M-F

Phone: (305) 852-7145

Recording Tips for Monroe County:
  • Ask if they accept credit cards - many offices are cash/check only
  • Recording fees may differ from what's posted online - verify current rates
  • Recorded documents become public record - avoid including SSNs
  • Ask about their eRecording option for future transactions

Cities and Jurisdictions in Monroe County

Properties in any of these areas use Monroe County forms:

  • Big Pine Key
  • Islamorada
  • Key Colony Beach
  • Key Largo
  • Key West
  • Long Key
  • Marathon
  • Marathon Shores
  • Summerland Key
  • Tavernier

View Complete Recorder Office Guide

Hours, fees, requirements, and more for Monroe County

How do I get my forms?

Forms are available for immediate download after payment. The Monroe County forms will be in your account ready to download to your computer. An account is created for you during checkout if you don't have one. Forms are NOT emailed.

Are these forms guaranteed to be recordable in Monroe County?

Yes. Our form blanks are guaranteed to meet or exceed the applicable formatting requirements used for recording in Monroe County, including margin requirements, font requirements, and other layout standards. This guarantee applies to formatting, not to the legal sufficiency of information entered by the user or the suitability of a form for a particular transaction.

Can I reuse these forms?

Yes. You can reuse the forms for your personal use. For example, if you have multiple properties in Monroe County you only need to order once.

What do I need to use these forms?

The forms are PDFs that you fill out on your computer. You'll need Adobe Reader (free software that most computers already have). You do NOT enter your property information online - you download the blank forms and complete them privately on your own computer.

Are there any recurring fees?

No. This is a one-time purchase. Nothing to cancel, no memberships, no recurring fees.

How much does it cost to record in Monroe County?

Recording fees in Monroe County vary. Contact the recorder's office at (305) 294-4641 for current fees.

Questions answered? Let's get started!

The Florida Conditional Waiver and Release of Lien upon Progress Payment is the lienor-protective counterpart to the unconditional progress waiver in section 713.20 of the Florida Statutes. With this version, the release is contingent: the lien rights described in the form are released only when the identified progress payment is actually received and clears. If the customer's check bounces, is stopped, or never arrives, the waiver does not take effect and the lienor's lien rights remain intact. Florida codified four statutory waiver scenarios precisely so that lienors and payors can match the right risk allocation to the situation, and the conditional progress waiver is the standard choice when a contractor, subcontractor, or supplier wants to deliver a release simultaneously with the act of being paid without taking on the credit risk of the payment instrument.

What the Florida Conditional Waiver and Release of Lien upon Progress Payment Does

This form is exchanged on a Florida construction project by a lienor — anyone with a right to claim a construction lien under chapter 713 — for a specific interim payment toward labor, services, or materials furnished through a stated date. Calling it "conditional" means the lien release is contingent on actual receipt and clearance of the payment; calling it "progress" means it covers a partial billing during an ongoing job, not the closeout. It is the form most commonly used to accompany a monthly pay application, because it lets the lienor deliver a signed waiver alongside the request for payment without losing the leverage of the underlying lien rights if the funds never land.

Florida Statutory Requirements Under Section 713.20

Florida is one of a handful of states that legislates the wording of construction lien waivers. Section 713.20 sets out specific statutory text for four scenarios — conditional or unconditional, paired with progress or final payment — and instructs that any waiver "substantially follow" the language of the matching statutory form. A waiver that materially deviates from the statutory wording, or that mixes language from a different scenario, may not be treated as a section 713.20 waiver at all. That distinction matters because the statute supplies the conditional language that ties the release to receipt of the payment; rewriting it can quietly convert a conditional waiver into something that operates as an unconditional release, or into a generic contractual document with uncertain effect.

The form must identify the lienor, the customer, the property owner, the amount of the conditional payment, the date through which the waiver applies, and a description of the property — typically the parcel identifier and legal description (§ 713.20).

Execution: No Witnesses, No Notary Required

Statutory waiver forms under section 713.20 do not require witnesses, notarization, or an acknowledgment to be effective. The lienor signs and dates the form, and it is delivered as part of the payment exchange. This is a deliberate departure from the formality required for Florida deeds, which need two witnesses and a notary; lien waivers move with the payment cycle on a job, and the legislature kept the execution requirements light. Some construction lenders and large general contractors require notarized waivers as a matter of internal policy. A notarized waiver is not invalid — the statute simply does not require notarization to make a section 713.20 waiver effective.

Florida-Specific Traps

Several features of the conditional progress waiver routinely surprise out-of-state contractors and owners:

  • Advance waivers are void. Florida law prohibits waiving the right to claim a lien before the underlying labor, services, or materials are furnished. A waiver tied to work the lienor has not yet performed is unenforceable to that extent (§ 713.20).
  • "Substantially follow" is a real test. A waiver missing a required field, or with the conditional language watered down, may not function as a section 713.20 conditional waiver. The customer who accepts a non-conforming waiver may have to pay twice if the underlying check is dishonored and the lienor's lien rights were never actually released.
  • The condition is automatic. The customer does not have a clean release in hand until the payment actually clears. This is the trade-off baked into a conditional waiver — the lienor stays protected, but the payor cannot use the waiver alone as proof that lien exposure has been eliminated for the period covered. Final closeouts and lender funding reviews often demand unconditional waivers for that reason.
  • Through date discipline. The form covers work through a stated date. A blank, postdated, or sloppily chosen through date can release more or less than the parties intended and creates evidentiary problems if the project later goes into dispute.
  • Notice of Commencement alignment. Florida requires the owner to record a Notice of Commencement on most private projects before construction begins (§ 713.13). The property described in the waiver should match the property described in the Notice of Commencement so that waivers can be tied back to the underlying job.
  • Joint check timing. If the progress payment is delivered by joint check, the conditional waiver only takes effect when the lienor is actually paid its share. A signed waiver does not bypass the joint payee's endorsement requirement.

How the Waiver Is Used

The conditional progress waiver is not recorded in the county's official records. It is delivered to the party making the payment — typically the general contractor, owner, or construction lender — and kept with the draw documentation. Because the release is contingent on payment receipt, owners and lenders often track conditional waivers against bank confirmations of cleared funds, and may swap them for unconditional waivers once the check has actually cleared. That two-step approach is common on jobs where the lender insists on documenting unconditional releases for audit purposes.

Download Package

The download package includes the Florida Conditional Waiver and Release of Lien upon Progress Payment, drafted to follow the statutory wording at section 713.20, a completed example showing how each field is filled in, and a guide explaining the form's conditional structure, the statutory framework, and how the four section 713.20 waiver scenarios fit together. The forms are prepared by Deeds.com's forms development team and are delivered as instant downloads.

Important: Your property must be located in Monroe County to use these forms. Documents should be recorded at the office below.

This Conditional Waiver and Release of Lien upon Progress Payment meets all recording requirements specific to Monroe County.

Our Promise

The documents you receive here are guaranteed to meet or exceed the applicable Monroe County recording format requirements. If there is a rejection caused by our formatting, we will correct the issue or refund your payment. This guarantee applies to document formatting only and does not extend to information entered by the user, the selection of the form, or the legal effect of the completed document.

Save Time and Money

Get your Monroe County Conditional Waiver and Release of Lien upon Progress Payment form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.

4.8 out of 5 - ( 4713 Reviews )

Meredith B.

January 5th, 2021

Clean and easy process. Super attentive and helpful.

Reply from Staff

Thank you!

Yehong M.

November 27th, 2019

everything worked well,

Reply from Staff

Thank you!

John S.

May 20th, 2023

Easy to use website and reasonably priced forms. I recommend it.

Reply from Staff

Thank you for the kind words John.

Scott D.

March 31st, 2025

I am very satisfied with the quality of the product I ordered. I have done similar property transfers/recording in the past on my own but paying for the forms and guidance is well worth it. The AI question area is extremely helpful. The example for the forms is perfect (as it has to be). I will absolutely use Deeds.com in the future for any related property needs. A+

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Thomas B.

May 29th, 2020

My deeds were filed with Pinellas County Florida with a simple process and with no problems. 5 star for sure.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Roger E.

August 30th, 2019

I have not yet used the product, but am confident that I will like it, because of this prompt request for a product review.

Reply from Staff

Thank you for your feedback. We really appreciate it. Have a great day!

Terry C.

July 29th, 2021

It is a difficult challenge -- trying to take the needless jargon out of legal transactions so ordinary citizens can manage their affairs. Deeds.com hasn't solved all the problems, but has made a super effort to help us achieve self-sufficiency.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

ALYSSA J.

August 26th, 2020

I was unable to end up going through with the deed process on my own as it was out of my realm. I suspect if I knew what I was actually doing when completing a deed, it would of been sufficient. I ended up having to go through an attorney to complete the deed.

Reply from Staff

Glad to hear you sought the assistance of a legal professional familiar with your specific situation, we always recommend that to anyone who is not completely sure of what they are doing. Have a wonderful day.

Kimberly M.

December 5th, 2019

I love Deeds.com. I've never had any issues with the service, getting documents back, etc.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Jearsel W.

January 5th, 2019

I was surprised how helpful the completed example was. It was nice to see what the form should look like when it is filled out. Great job!

Reply from Staff

That's wonderful to hear Jearsel, thanks for your feedback. Have an awesome day.

Peggy G.

May 19th, 2019

This is an easy document to complete and file. Thank you for having the completed sample for review.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

James K.

January 12th, 2023

Gave me exactly what i needed

Reply from Staff

Thank you for your feedback. We really appreciate it. Have a great day!

Viviana Hansen M.

March 3rd, 2024

I was thrilled that I could execute the paperwork for a lady bird deed here in Florida ! Thank you

Reply from Staff

We are grateful for your feedback and looking forward to serving you again. Thank you!

Ken W.

February 3rd, 2019

Everything perfect, good price. Completely satisfied

Reply from Staff

Thank you!

Richard P.

April 18th, 2020

Excellent source and easy to use site.

Reply from Staff

Thank you!