Cumberland County Conditional Lien Waiver on Progress Payment Forms (Maine)

Express Checkout

Form Package

Conditional Lien Waiver on Progress Payment

State

Maine

Area

Cumberland County

Price

$27.97

Delivery

Immediate Download

Payment Information

Please provide a valid email.
Please provide a valid first name.
Please provide a valid last name.
Please provide a valid card number.
Please provide a valid security code.
Please provide a valid billing zip code.
You must agree before submitting.
More info on getting a copy of your existing deed and eRecording.

Included Forms

All Cumberland County specific forms and documents listed below are included in your immediate download package:

Conditional Lien Waiver on Progress Payment Form

Conditional Lien Waiver on Progress Payment Form

Fill in the blank Conditional Lien Waiver on Progress Payment form formatted to comply with all Maine recording and content requirements.
Included document last reviewed/updated 4/11/2024

Conditional Lien Waiver on Progress Payment Guide

Conditional Lien Waiver on Progress Payment Guide

Line by line guide explaining every blank on the form.
Included document last reviewed/updated 4/12/2024

Completed Example of the Conditional Lien Waiver on Progess Payment Document

Completed Example of the Conditional Lien Waiver on Progess Payment Document

Example of a properly completed form for reference.
Included document last reviewed/updated 12/26/2023

Frequently Asked Questions:

How long does it take to get my forms?

Forms are available immediately after submitting payment.

What are supplemental forms?

Often when a deed is recorded, additional documents are required by Maine or Cumberland County. These could be tax related, informational, or even as simple as a coversheet. Supplemental forms are provided for free with your order where available.

How do I get my forms, are they emailed?

Forms are NOT emailed to you. Immediately after you submit payment, the Cumberland County forms you order will be available for download directly from your account. You can then download the forms to your computer. If you do not already have an account, one will be created for you as part of the order process, and your login details will be sent to you. If you encounter any issues accessing your forms, please reach out to our support team for assistance.

What type of files are the forms?

All of our Cumberland County Conditional Lien Waiver on Progress Payment forms are PDFs. You will need to have or get Adobe Reader to use our forms. Adobe Reader is free software that most computers already have installed.

Can the Conditional Lien Waiver on Progress Payment forms be re-used?

Yes. You can re-use the forms for your personal use. For example, if you have more than one property in Cumberland County that you need to transfer you would only need to order our forms once for all of your properties in Cumberland County.

Are these forms guaranteed to be recordable in Cumberland County?

Yes. Our form blanks are guaranteed to meet or exceed all formatting requirements set forth by Cumberland County including margin requirements, content requirements, font and font size requirements.

Do I have to enter all of my property information online?

No. The blank forms are downloaded to your computer and you fill them out there, at your convenience.

Can I save the completed form, email it to someone?

Yes, you can save your deed form at any point with your information in it. The forms can also be emailed, blank or complete, as attachments.

Do I need any special software to use these forms?

You will need to have Adobe Reader installed on your computer to use our forms. Adobe Reader is free software that most computers already have installed.

Are there any recurring fees involved?

No. Nothing to cancel, no memberships, no recurring fees.

Areas Covered by These Conditional Lien Waiver on Progress Payment Forms:

  • Cumberland County

Including:

  • Bailey Island
  • Bridgton
  • Brunswick
  • Bustins Island
  • Cape Elizabeth
  • Casco
  • Chebeague Island
  • Cliff Island
  • Cumberland Center
  • Cumberland Foreside
  • East Baldwin
  • Falmouth
  • Freeport
  • Gorham
  • Gray
  • Harpswell
  • Harrison
  • Long Island
  • Naples
  • New Gloucester
  • North Bridgton
  • North Yarmouth
  • Orrs Island
  • Peaks Island
  • Portland
  • Pownal
  • Raymond
  • Scarborough
  • Sebago
  • South Casco
  • South Freeport
  • South Portland
  • South Windham
  • Standish
  • Steep Falls
  • West Baldwin
  • Westbrook
  • Windham
  • Yarmouth

What is the Maine Conditional Lien Waiver on Progress Payment

Mechanic's liens are governed under Title 10, Chapter 603 of the Maine Code. A waiver is a forfeiture or "giving up" of a legal right. In this case, the person granting the waiver is giving up the right to seek a mechanic's lien for all or part of the amount due. This assurance is usually enough to get the other party to pay. The Maine Code does not set out statutory forms for waivers, but according to the principles of contract law, the parties may agree to such modifications in writing.

In general, there are four types of waivers: conditional or unconditional, and referring to a partial or final payment. Conditional waivers become effective when the payment is confirmed (paid) by the bank, and offer more protection for the contractor. Unconditional waivers go into effect immediately, regardless of whether or not the payment is confirmed, and give more protection for the property owner. Partial, or progress payments relate to specific time frames or completed steps in the project. Final payment waivers apply when the responsible party pays the entire balance due.

In a situation where a property owner pays for work completed to date on a continuing project, the owner might request a lien waiver from the contractor, affirming that the contractor will not file a mechanic's lien for the remaining debt. Partial waivers relinquish lien rights for up to the partial or progress payment amount. A conditional waiver means the waiver is conditioned upon the claimant receiving the amount due. So, the contractor can offer a partial conditional waiver when the owner makes less than the full or final payment and the payment method does not guarantee receipt of the money (such as a check that hasn't cleared yet). This protects the owner's interests, and if the contractor is not entirely confident about the status of the payment, she can offer a conditional waiver and safeguard her rights, too.

Lien waivers identify the parties, the location of the project, relevant dates, and amounts paid. Record the signed, notarized waiver in the local recording office, and deliver a certified copy of the recorded document to the property owner.

This article is provided for informational purposes only and should not be relied upon as a substitute for the advice from an attorney. Please contact a Maine attorney with any questions about waiving lien rights or anything else with regard to mechanic's liens.

Our Promise

The documents you receive here will meet, or exceed, the Cumberland County recording requirements for formatting. If there's an issue caused by our formatting, we'll make it right and refund your payment.

Save Time and Money

Get your Cumberland County Conditional Lien Waiver on Progress Payment form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.

Reviews

4.8 out of 5 (4324 Reviews)

Michael L.

April 25th, 2024

Professional, simple. Very good.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Barbara A.

April 25th, 2024

Always helpful!\r\n

Reply from Staff

We are thankful for your continued support and feedback, which inspire us to continuously improve. Thank you..

Mark E.

April 25th, 2024

This was easy to use and only contained one glaring error-where to send the completed form to finish the process. I’ve completed the form, does this mean I get the amended deed sent to me? I think not.

Reply from Staff

Your insights are invaluable to us and help us strive for better service. Thank you for taking the time to share your thoughts.

Irma D.

June 14th, 2021

Very impressed with the Service in Miami-Dade County. THank you

Reply from Staff

Thank you!

Myrna P.

March 18th, 2019

Easy to download, form very user friendly, and its customized to our county. Very much worth the money.

Reply from Staff

Thank you Myrna. Have a fantastic day!

jim g.

June 4th, 2020

so far so good. was hoping to have the recorded document already. i need the recorded document by friday, june 5th for my city approval. anyway you can please get it to me tomorrow.
thanks,
jim

Reply from Staff

Thank you!

Gloria H.

December 17th, 2020

Very content with the service received. The document was recorded in the city in no time. Will definitely use Deeds.com again in the near future.

Reply from Staff

Thank you!

LeRoy E.

June 20th, 2022

So thankful I found this. I was feeling stressed out and reluctant about doing this on my own.

Reply from Staff

Thank you!

Maxine P.

August 24th, 2020

This is so amazing and I truly thank you for what I needed for my documents. This is a great company and will take care of what you needs.

Reply from Staff

Thank you for your feedback. We really appreciate it. Have a great day!

Geoffrey M.

February 17th, 2021

Very convenient online document recording with great and quick service. Thank you!

Reply from Staff

Thank you!

Winifred T.

May 18th, 2021

ive been looking for this information thank you .

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Arturo P.

August 16th, 2021

Super easy to use! Totally satisfied. Thanks.

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!

Jill A.

March 26th, 2021

Finding current forms in one place helps simplify the process. Thank you.

Reply from Staff

Thank you!

Michael H.

April 8th, 2020

Very responsive and thorough. Glad to have found such a great company for our recording needs.

Reply from Staff

Thank you!

IVAN G.

August 21st, 2020

THIS Guys Save YOU TIME , Efforts and MONEY!!! So easy and secured to use,,NOT to mention FAST!!

Reply from Staff

We appreciate your business and value your feedback. Thank you. Have a wonderful day!