Conditional Lien Waiver on Progress Payment Guide

Line by line guide explaining every blank on the form.
Included Lincoln County compliant document last validated/updated 4/22/2025
Completed Example of the Conditional Lien Waiver on Progess Payment Document

Example of a properly completed form for reference.
Included Lincoln County compliant document last validated/updated 3/10/2025
The following Maine and Lincoln County supplemental forms are included as a courtesy with your order:
When using these Conditional Lien Waiver on Progress Payment forms, the subject real estate must be physically located in Lincoln County. The executed documents should then be recorded in the following office:
Registry of Deeds
County Courthouse - 32 High St, Wiscasset, Maine 04578
Hours: 8:00 to 4:00 Monday through Friday / Recording until 3:30
Phone: (207) 882-7431
Local jurisdictions located in Lincoln County include:
- Alna
- Boothbay
- Boothbay Harbor
- Bremen
- Bristol
- Chamberlain
- Coopers Mills
- Damariscotta
- Dresden
- East Boothbay
- Edgecomb
- Isle Of Springs
- Jefferson
- Monhegan
- New Harbor
- Newcastle
- Nobleboro
- Pemaquid
- Round Pond
- South Bristol
- Southport
- Squirrel Island
- Trevett
- Waldoboro
- Walpole
- West Boothbay Harbor
- Whitefield
- Wiscasset
How long does it take to get my forms?
Forms are available immediately after submitting payment.
How do I get my forms, are they emailed?
Immediately after you submit payment, the Lincoln County forms you order will be available for download directly from your account. You can then download the forms to your computer. If you do not already have an account, one will be created for you as part of the order process, and your login details will be provided to you. If you encounter any issues accessing your forms, please reach out to our support team for assistance. Forms are NOT emailed to you.
What does "validated/updated" mean?
This indicates the most recent date when at least one of the following occurred:
- Updated: The document was updated or changed to remain compliant.
- Validated: The document was examined by an attorney or staff, or it was successfully recorded in Lincoln County using our eRecording service.
Are these forms guaranteed to be recordable in Lincoln County?
Yes. Our form blanks are guaranteed to meet or exceed all formatting requirements set forth by Lincoln County including margin requirements, content requirements, font and font size requirements.
Can the Conditional Lien Waiver on Progress Payment forms be re-used?
Yes. You can re-use the forms for your personal use. For example, if you have more than one property in Lincoln County that you need to transfer you would only need to order our forms once for all of your properties in Lincoln County.
What are supplemental forms?
Often when a deed is recorded, additional documents are required by Maine or Lincoln County. These could be tax related, informational, or even as simple as a coversheet. Supplemental forms are provided for free with your order where available.
What type of files are the forms?
All of our Lincoln County Conditional Lien Waiver on Progress Payment forms are PDFs. You will need to have or get Adobe Reader to use our forms. Adobe Reader is free software that most computers already have installed.
Do I need any special software to use these forms?
You will need to have Adobe Reader installed on your computer to use our forms. Adobe Reader is free software that most computers already have installed.
Do I have to enter all of my property information online?
No. The blank forms are downloaded to your computer and you fill them out there, at your convenience.
Can I save the completed form, email it to someone?
Yes, you can save your deed form at any point with your information in it. The forms can also be emailed, blank or complete, as attachments.
Are there any recurring fees involved?
No. Nothing to cancel, no memberships, no recurring fees.
Mechanic's liens are governed under Title 10, Chapter 603 of the Maine Code. A waiver is a forfeiture or "giving up" of a legal right. In this case, the person granting the waiver is giving up the right to seek a mechanic's lien for all or part of the amount due. This assurance is usually enough to get the other party to pay. The Maine Code does not set out statutory forms for waivers, but according to the principles of contract law, the parties may agree to such modifications in writing.
In general, there are four types of waivers: conditional or unconditional, and referring to a partial or final payment. Conditional waivers become effective when the payment is confirmed (paid) by the bank, and offer more protection for the contractor. Unconditional waivers go into effect immediately, regardless of whether or not the payment is confirmed, and give more protection for the property owner. Partial, or progress payments relate to specific time frames or completed steps in the project. Final payment waivers apply when the responsible party pays the entire balance due.
In a situation where a property owner pays for work completed to date on a continuing project, the owner might request a lien waiver from the contractor, affirming that the contractor will not file a mechanic's lien for the remaining debt. Partial waivers relinquish lien rights for up to the partial or progress payment amount. A conditional waiver means the waiver is conditioned upon the claimant receiving the amount due. So, the contractor can offer a partial conditional waiver when the owner makes less than the full or final payment and the payment method does not guarantee receipt of the money (such as a check that hasn't cleared yet). This protects the owner's interests, and if the contractor is not entirely confident about the status of the payment, she can offer a conditional waiver and safeguard her rights, too.
Lien waivers identify the parties, the location of the project, relevant dates, and amounts paid. Record the signed, notarized waiver in the local recording office, and deliver a certified copy of the recorded document to the property owner.
This article is provided for informational purposes only and should not be relied upon as a substitute for the advice from an attorney. Please contact a Maine attorney with any questions about waiving lien rights or anything else with regard to mechanic's liens.
Our Promise
The documents you receive here will meet, or exceed, the Lincoln County recording requirements for formatting. If there's an issue caused by our formatting, we'll make it right and refund your payment.
Save Time and Money
Get your Lincoln County Conditional Lien Waiver on Progress Payment form done right the first time with Deeds.com Uniform Conveyancing Blanks. At Deeds.com, we understand that your time and money are valuable resources, and we don't want you to face a penalty fee or rejection imposed by a county recorder for submitting nonstandard documents. We constantly review and update our forms to meet rapidly changing state and county recording requirements for roughly 3,500 counties and local jurisdictions.
4.8 out of 5 - ( 4558 Reviews )
Loretta W.
June 26th, 2025
Thank you for your excellent service
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Nigel S.
June 24th, 2025
Very simple to use. The 'completed examples' are very helpful.
Thank you for your feedback. We really appreciate it. Have a great day!
Robert H.
June 23rd, 2025
Great service, easy way to get accurate documents
Thanks, Robert! We're glad you found the service easy to use and the documents accurate—just what we aim for. Appreciate you taking the time to share your experience!
Jim J.
February 8th, 2019
The forms were easy to use and the fields are tabbed so that you can enter your information and then move quickly to the next entry. The Guide for the documents was very helpful.
Thanks Jim, we appreciate your feedback.
JoAnn T.
October 7th, 2022
Very happy! This was a very easy to use web site, the form came with directions and an example, both were very helpful. I will absolutely use Deeds.com in the future.
Thank you for your feedback. We really appreciate it. Have a great day!
Victor W.
March 9th, 2022
Once I was able to get the code Number, it all went well. I was able to easily download and print off what I needed for my lawyer.
thank you.
Thank you!
HELEN F.
September 1st, 2019
Process was easy... paperwork was on point... process took less then one day...
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Andre W.
May 20th, 2020
I was truly impress with the customer service. The young lady that assisted me was AWESOME. She was very professional,patienc was extraordinary and very knowledgable. Thank you thank you
Thank you for your feedback. We really appreciate it. Have a great day!
Linda P.
January 27th, 2022
Once I found this site the rest was easy. I read through the guide but the example really helped the most. Very easy!!!
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
ROBERT L.
April 1st, 2019
I got a blank, a sample and detailed instructions, I'm happy. If the recorder's office had a form as they like to see, with your name as they like to see, and the property name as they like to see, no one would ever pay a lawyer for this but a little time to look up the exact names and this package you're all set. I recommend this because, while it isn't difficult, making a mistake could be very bad so getting the details right for a particular county is well worth the cost.
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
TAMMIE M.
November 20th, 2020
The site worked well for me.
Thank you!
David P.
August 26th, 2020
Easy to use and very straight forward. Glad I used Deeds.com
We appreciate your business and value your feedback. Thank you. Have a wonderful day!
Katherine M.
June 26th, 2019
Very helpful!
Thank you!
Hilary C.
October 9th, 2020
Within 10 minutes I had my Deed!!! Fantastic!!!!
Thank you for your feedback. We really appreciate it. Have a great day!
Debbie G.
February 2nd, 2019
Easy to use, I would recommend deeds.com. I would recommend visiting your county recorder before having document notarized. They will review document and make sure everything you need is on the deed, before having notarized.
Thank you Debbie. Have a fantastic day!